Topological Sort for Task Scheduling

Difficulty: Medium · Topics: Graph, Topological Sort, BFS · Acceptance: 100.0% of 1 submissions

Difficulty: Medium  |  Tags: Graph, BFS, Topological Sort

Description

Given n tasks labeled 0 to n-1 and a list of dependencies [a, b] (meaning task b must finish before task a), return a valid order to complete all tasks — or indicate that it's impossible (cycle detected).

Implement:

taskSchedule(numTasks, dependencies) → int[]

Examples

Example 1:

Input:  numTasks = 4, deps = [[1,0], [2,0], [3,1], [3,2]]
Output: [0, 1, 2, 3] or [0, 2, 1, 3]

Example 2 — Impossible:

Input:  numTasks = 2, deps = [[0,1], [1,0]]
Output: [] (cycle detected)

Example 3 — No dependencies:

Input:  numTasks = 3, deps = []
Output: [0, 1, 2] (or any order)

Constraints

Hints

Hint 1

Classic topological sort. Use Kahn's algorithm with in-degree counting and BFS queue.